C. Sequence of Operation Charts
1. Cabinet Cooling
Legend:
CabFM-cabinet fan motor
Comp-compressor
ConFM-condenser fan motor
CLLV-cabinet liquid line valve
CTh-cabinet thermistor
DH-defrost heater
DT-defrost timer
DTh-defrost thermistor
DTst-defrost thermostat
PH-perimeter heater
CabFM energized
CLLV energized
PH energized
Comp de-energized
ConFM de-energized
4. Cabinet Defrost
1. Startup 2. Cool Down 3. Cool Down Achieved
CabFM energized
CLLV energized
Comp energized
ConFM energized
PH energized
CTh in control
DTh reaches 49°F (9.4°C) or
100-minute defrost termination timer expires or
DTst temperature reaches 120°F±5°F (49°C±3°C)
CabFM energized
CLLV energized
PH energized
CTh warms to
setpoint
•2‑minute
Comp delay
timer starts
•6‑hourDT
starts
5. Cabinet Cool Down Defrost Recovery
(defrost terminated)
CabFM energized
CLLV energized
Comp energized
ConFM energized
PH energized
Stage 1:
5-minute Comp
delay timer
DTh in control
To 5 below
From 5 below
To 2 above
From 4
above
•6hourDTexpires,then
resets
•100‑minutedefrost
termination timer starts
CabFM and PH
energize for 10 sec.
CLLV energized
Comp energized
ConFM energized
Stage 2:
5-minute CabFM and
PH delay timer
Power Switch "ON," Rail Cooling Switch "OFF"
CLLV energized
DH energized
CabFM de-energized
Comp de-energized
ConFM de-energized
PH de-energized
CLLV energized
DH de-energized
CabFM de-energized
Comp de-energized
ConFM de-energized
PH de-energized
CTh reaches
3.6°F (2°C)
or more
below setpoint
2-minute Comp
delay timer starts
Cycle Steps
Initial startup
begins here